By: Jeremy Clow
The
warming weather of spring has provided great opportunities for construction at
touch of nature. Continuing in my ARC 502 elective course with professor
Schwartz we have started the construction process for the graduate site as well
as administered the undergraduate constructions. After two successful build
days the undergraduate’s six sites have all foundation, and structural elements
constructed and installed. Minor details and pieces requiring prefabrication
are underway as well. The first build day, was a very warm and sunny day
however the previous rains made some trail movement difficult. Carrying
construction elements, tools, and materials up and down steep mud packed trails
proved to be a difficult task for the sophomores. By the end of the day however
the majority of the footings had been poured, columns in place, and structural
beams installed.
Each site has a small group of students assigned to it, around
five or six people per location. With each location having a cohesion of signage
along the trail but a different program or discussion at each location. The
constructions have similarities in materials and assembly methods to provide a
big picture cohesion for future programming. The second build day, Tuesday
April 12th however took place after a series of rainy days. The
April showers made travel on the trails difficult beyond comparison.
Transporting the large structural components, seating, and signage by foot is
troublesome on its own due to the inclination and quality of the trails.
Vehicular access on the trail was limited to one, my Jeep due to the conditions
as well as to limit the amount of wear and tear on the trail. Due to these
natural elements upon the 8am arrival start time the first half of the day was
dedicated to prefabrication on an asphalt parking lot surrounding the wood
shop. At this location the tools are easily accessible as well as electricity
for powering them. The ground condition is solid and the tree coverage is
minimal. Here the solar heat gain not only helps dry the materials but warms
the bodies working on site as well. The sites located near the beach have the
most solar exposure during the early hours with their shore facing South East.
Therefor we were able to get started on their site location with ease early in
the morning. My particular group has site 6, located at the end of a peninsula
protruding into Little Grassy Lake. The access road, trail, and site are well
protected and shaded by tree cover. An appealing feature in most situations
however troublesome after the rain. During the beginning of the day we started
and completed the construction of our bench as well as the four pieces of
signage. All of the pieces prefabricated at the wood shop were done shortly
after lunch. With the site starting to warm up as well as dry up the trail
became more and more passible by the hour. We finished the day transporting the
various materials for the groups down the trail and stored them on site in
preparation for the next build day. The next build day is scheduled for this
Saturday, after the current and coming warm weather it should be a great day
for final installations and finishing touches.
No comments:
Post a Comment